Client: FLUOR / BASF – Ludwigshafen in Germany

Market: Process / EPC

Scope: Piping pre-fab including painting, piping & equipment erection,  electrical and steam tracing, insulation, scaffolding and fabrication of column internals

Key figures: Contract size: Below €300M (confidential)

Major dates:

  • November 2013: contract signed
  • February 2015: transition from unit rate to time & material
  • November 2015: commissioning
  • June 2016: installation of insulation boxes for valves and flanges and completion of all remaining works

Key-features:

  • The new plant is the first facility in the world, which is able to produce 300,000 tons per year in only one single-stranded production line
  • Hertel achieved more than 3.0 million hours LTI-free
  • The manpower load was at the highest in week 12 with a total of approximately 1,423 personnel (including overhead)